Before CBDRR STUDY
Activities of the project ( IHDT completed)
Planted Grass along the feeder cannel
Manufactured and fixed two water gates to main feeder canal
Removed invasive plants of the area to plant suitable tree species
Constructed a natural wall to protect school from floods
Excavated earth for the construction of new tank and Planted grass in the tank bunt